RIYADH: Dubai Electricity and Water Authority has completed 93 percent of the 829 megawatts fourth phase of the H-Station power plant in Al Aweer with investments totaling 1.1 billion dirhams ($30 million).
This phase will increase Al Aweer Power Station Complex’s total capacity to 2,825 MW under climate conditions of 50 degrees Celsius and 30 percent relative humidity. Key testing and commissioning operations have started in the fourth quarter of 2022. The project is expected to be operational in the first quarter of 2023.